what is the difference between n(not running) and d(done) conditions in autosys?

user3055262 picture user3055262 · Dec 12, 2014 · Viewed 14.7k times · Source

I am aware that the done(d) condition would be TRUE when the job is in SU, TE, FA status. I would like to understand the same for n, and so the difference between n and d conditions.

Answer

Oleksandr Kucher picture Oleksandr Kucher · Dec 18, 2014

The "notrunning" condition will be TRUE when the status of the job on which it is dependent is anything except RUNNING.