I'm curious as to what other people use for physical Kanban/Scrum boards in their companies. I appreciate that because of sensitive business information you may not be able to provide a photo of the board. I"m looking at to find out what does your board looks like, and how you organize user stories and tasks as they move through a typical sprint/iteration?
Typically I've worked in a places that organize the board as follows with each
User Story | Todo | In Progress | Ready for QA | Done |
UC-001 | Domain Object, Service | DAO(Bob) | | |
UC-002 | Payment UI Screen | | Payment Srv (Don)| |
UC-003 | | | UC-003 | |
| | | | UC-004 |
| | | | UC-005 |
So to summarise:
This works as a tangible white board that involves people interacting with each of the tasks/user stories (represented as post it notes). An electronic version is created prior to the sprint/iteration and is only updated at the end of the sprint/iteration corresponding to the current situation. Comments and criticism are welcomed : )
We use something inspired by the famous Scrum and XP from the Trenches from Henrik Kniberg, the columns being adapted depending on the context (often: TODO, ON GOING, TO BE TESTED, DONE):
alt text http://blog.realcoderscoding.com/wp-content/uploads/2008/09/hk.png
Product Backlog Items (PBIs) are printed as "physical cards" (A5 format) for the Sprint Planning Meeting (at least the most important). Once the team has picked up PBIs for the next iteration, items are break down into tasks/activities (on sticky notes). After the meeting, everything goes on the Scrum Board and I suggest to use tape or thumbtacks or magnets. PBIs are ordered by importance, most important at the top of the board, less important at the bottom. The team should work on the most important item first until it gets done. First, activity post-its move from the left to the right. Then, the PBI jumps to Done. Unexpected tasks are added to an "Unplanned items" zone (to take them into account in the burndown chart). Future PBIs stay visible in a "Next" zone (if all items are completed during the iteration, we pick a new one from there). Pretty simple.
These practices allow to detect smells visually, for example:
Works great.
If you are looking for more "kanban oriented" stuff, maybe have a look at Kanban vs Scrum, One day in Kanban Land and Kanban and Scrum - a practical guide from the same Henrik Kniberg. Great stuff too.
And, for more pictures, give Google Images a try with scrum+board, kanban, scrumban, scrum+kanban.