I'm in the middle of calculating week numbers for dates, but the System.Globalization.Calendar is returning odd results for (amongst other years) December 31st of year 2007 and 2012.

Calendar calendar = CultureInfo.InvariantCulture.Calendar;
var date = new DateTime(2007, 12, 29);
for (int i = 0; i < 5; i++)
{
    int w = calendar.GetWeekOfYear(date, CalendarWeekRule.FirstFourDayWeek, DayOfWeek.Monday);
    Console.WriteLine("{0}\t{1}", date.ToString("dd.MM.yyyy"), w);
    date = date.AddDays(1);
}

Results

29.12.2007      52
30.12.2007      52
31.12.2007      53 <--
01.01.2008       1
02.01.2008       1

29.12.2012      52
30.12.2012      52
31.12.2012      53 <--
01.01.2013       1
02.01.2013       1

As far as I understand, there shouldn't be a week 53 in year 2007 and 2012, but the days should be included in week 1. Is there a way to change this behaviour in the Calendar?

Answer

phoog picture phoog · Jan 10, 2012

The documentation for the CalendarWeekRule enumeration specifically states that it "does not map directly to ISO 8601", and links to ISO 8601 Week of Year format in Microsoft .Net, a blog entry that describes the differences.